Wells College Video Promotion Project
|
Name |
Begin date |
End date |
Resources |
Prepare Making
|
4/10/21
|
8/10/21
| |
Made Script
|
4/10/21
|
4/10/21
| John |
Location Select
|
5/10/21
|
6/10/21
| John, Jack |
Get Machine
|
6/10/21
|
8/10/21
| James, Video Camera |
Start Recording
|
11/10/21
|
15/10/21
| |
Campus
|
11/10/21
|
11/10/21
| John |
Classroom
|
12/10/21
|
13/10/21
| John |
Network System
|
14/10/21
|
14/10/21
| Jack |
Enviroment
|
11/10/21
|
15/10/21
| John, James |
Final The Video
|
18/10/21
|
22/10/21
| |
Add sound
|
18/10/21
|
20/10/21
| Jack |
Edit Tape
|
20/10/21
|
21/10/21
| James |
Review All
|
22/10/21
|
22/10/21
| John |
Finish All
|
25/10/21
|
25/10/21
| John |
Ganttproject (3.1.3102) | ganttproject.biz
18/10/21 - 9:43:02 am |